June 2025

Stakeholder enagagement

Started engagement with residents on Zimin Drive to inform them of upcoming survey work and consult on crossing locations.

July 2025

Survey and Design Procurement

A land survey was undertaken and civil design procurement documentation was prepared 

September 2025

Design Procurement

Begin Civic Design procurement processes

November 2025

Construction documentation

Prepare construction procurenment documentation

March 2026

Start construction