18 June 2025

Design and Construct Tender awarded to Northern Building and Property Services

31 October 2025

Development Permit attained

17 March 2026

Estimated date for building permit

24 March 2026

Estimated date for Council approval to build

31 August 2026

Date of practical completion

01 September 2026

Latent condition contingency & post handover works - to 30 December 2026